How it is calculated
Maximum demand is the connected load in kVA times the demand factor. Add the spare you want for future load, divide by the planned maximum loading, and the next standard rating up is chosen from the R10 series (IEC, GB) or the ANSI/IEEE series.
Rated current I = S / (√3 × U). The short-circuit current at the secondary terminals is I_k = U / (√3 × Z) with Z the transformer impedance u_k × U² / S, plus the upstream impedance when you give the fault level. Without a nameplate value the minimum impedance of IEC 60076-5 Table 1 is used.
Questions
- How much spare capacity should a transformer have?
- Many designs plan for a maximum loading of 75–85 % plus 15–25 % for future load. Your utility or client may set their own figures.
- What is a demand factor?
- The share of the connected load that is on at the same time. A building with many small loads rarely runs them all at once, so the factor is often 0.6–0.8.
- Why does the short-circuit current matter?
- The main switchboard and breakers must be rated for it. A larger transformer or a lower impedance gives a higher fault current.
- Can I use it for single-phase transformers?
- Yes. Choose single-phase; with the ANSI series the single-phase ratings are used.
Other calculators
- kW to amps calculator
- Voltage drop calculator
- Cable size calculator
- Low-voltage short-circuit calculator
- High-voltage short-circuit calculator
- Earth resistance calculator
- Lightning rod height calculator
- Power factor correction calculator
- Generator size calculator
- Lighting calculator
- Battery capacity calculator
- PV string size calculator
- Pipe insulation thickness calculator
- Pipe flow and diameter calculator
- Pipe pressure drop calculator
- Pump power calculator
- Heat exchanger calculator